- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -
Hawk installation schedule: Difference between revisions
From HLRS Platforms
Jump to navigationJump to search
No edit summary |
mNo edit summary |
||
Line 8: | Line 8: | ||
| end of May 2019|| Installation of a small test system | | end of May 2019|| Installation of a small test system | ||
|- | |- | ||
| September 2nd ... 6th || Reduce Cray XC40 | | September 2nd ... 6th || Reduce Cray XC40 HazelHen to ~3800 Nodes and | ||
preparation infrastructure for Hawk (1st part) | preparation of infrastructure for Hawk (1st part) | ||
|- | |- | ||
| October 2019|| Installation of a few racks Hawk, storage, pre-post servers, | | October 2019|| Installation of a few racks Hawk, storage, pre-post servers, ... | ||
integration, testing, setup for users | integration, testing, setup for users | ||
|- | |- | ||
| November 2019 || Test Phase for pilot users ~ 4 weeks | | November 2019 || Test Phase for pilot users ~ 4 weeks | ||
|- | |- | ||
| December 2019 || | | December 2019 || Decommission of Hazel Hen and preparation of infrastructure for the | ||
complete installation Hawk | complete installation of Hawk | ||
|- | |- | ||
| later || complete Hawk hardware installation, testing, and integrate into | | later || complete Hawk hardware installation, testing, and integrate into | ||
first phase | |||
|- | |- | ||
| more later || Acceptance and production | | more later || Acceptance and production | ||
|} | |} |
Revision as of 19:17, 15 May 2019
This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
time frame | action |
---|---|
end of May 2019 | Installation of a small test system |
September 2nd ... 6th | Reduce Cray XC40 HazelHen to ~3800 Nodes and
preparation of infrastructure for Hawk (1st part) |
October 2019 | Installation of a few racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users |
November 2019 | Test Phase for pilot users ~ 4 weeks |
December 2019 | Decommission of Hazel Hen and preparation of infrastructure for the
complete installation of Hawk |
later | complete Hawk hardware installation, testing, and integrate into
first phase |
more later | Acceptance and production |