- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -
Hunter installation schedule: Difference between revisions
No edit summary |
No edit summary |
||
Line 21: | Line 21: | ||
| || installation phase finished | | || installation phase finished | ||
|} | |} | ||
The following illustration shows the current planning of the Hunter installation. Please note that the schedule is subject to change. | |||
[[File:240614-Hunter-Timeline.jpg|thumb|Installation planning as of June 2024]] |
Revision as of 08:22, 17 June 2024
This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
More information could be found [hpc in transition hunter and herder will bring new opportunities new challenges] and [supercomputing kommt nach stuttgart] fact-sheet can be found here.
time frame | action |
---|---|
June 18th - 19th | Hawk maintenance and preparation
of infrastructure (1st part). System will be reduced to 4096 compute nodes in total |
mid of August | delivery parts of Hunter |
January 31st | Acceptance Hunter and starting data migration onto new storage platform |
end of April | Hawk final power down |
installation phase finished |