Hunter installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
(Tabelle aktualisier)
 
(5 intermediate revisions by 2 users not shown)
Line 2: Line 2:
components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...


More information could be found [[https://www.hlrs.de/news/detail/hpc-in-transition-hunter-and-herder-will-bring-new-opportunities-new-challenges| hpc in transition hunter and herder will bring new opportunities new challenges]] and [[https://www.hlrs.de/de/news/detail/exascale-supercomputing-kommt-nach-stuttgart|exascale supercomputing kommt nach stuttgart]]
More information could be found [[https://www.hlrs.de/news/detail/hpc-in-transition-hunter-and-herder-will-bring-new-opportunities-new-challenges | hpc in transition hunter and herder will bring new opportunities new challenges]] and [[https://www.hlrs.de/news/detail/exascale-supercomputing-is-coming-to-stuttgart | exascale supercomputing is coming to stuttgart]]
fact-sheet can be found [[media:HLRS_Hunter_mit_Freigabe.pdf|here]].
fact-sheet can be found [[Media:HLRS Hunter mit Freigabe.pdf|here]].




Line 13: Line 13:
of infrastructure (1st part). System will be reduced to 4096 compute nodes in total
of infrastructure (1st part). System will be reduced to 4096 compute nodes in total
|-
|-
| September 3rd || delivery parts of Hunter (racks, cooling, mgmt-systems, ...)
| October 1st || delivery parts of Hunter (racks, APU and CPU nods, cooling, mgmt-systems, ...)
|-
|-
| November 18th || delivery of lustre filesystems
| early November || software installation and first application tests by pilot users. December 10st - first pilot users are active and are going to install additional HLRS provided software.
|-
|-
| Q4 / 2024 || System will be reduced by another 8 racks
| November 18th || delivery of lustre filesystems. December 9th - Lustre ws12 has been installed and will be tested for some time.
|-
|-
| January 31st || Acceptance Hunter and starting data migration onto new storage platform
| Q4 / 2024 || Hawk will be reduced by another 8 racks (if projects are active on Hunter). This step has been postponed until a proper use of Hunter is possible
|-
| January 31st 2025 || Acceptance Hunter and starting data migration onto new storage platform
|-
|-
| end of April 2025 || Hawk final power down
| end of April 2025 || Hawk final power down

Latest revision as of 09:17, 12 December 2024

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

More information could be found [| hpc in transition hunter and herder will bring new opportunities new challenges] and [| exascale supercomputing is coming to stuttgart] fact-sheet can be found here.


time frame action
June 18th - 19th Hawk maintenance and preparation

of infrastructure (1st part). System will be reduced to 4096 compute nodes in total

October 1st delivery parts of Hunter (racks, APU and CPU nods, cooling, mgmt-systems, ...)
early November software installation and first application tests by pilot users. December 10st - first pilot users are active and are going to install additional HLRS provided software.
November 18th delivery of lustre filesystems. December 9th - Lustre ws12 has been installed and will be tested for some time.
Q4 / 2024 Hawk will be reduced by another 8 racks (if projects are active on Hunter). This step has been postponed until a proper use of Hunter is possible
January 31st 2025 Acceptance Hunter and starting data migration onto new storage platform
end of April 2025 Hawk final power down
installation phase finished


The following illustration shows the current planning of the Hunter installation. Please note that the schedule is subject to change.

Installation planning as of June 2024