Hunter installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
 
(One intermediate revision by the same user not shown)
Line 15: Line 15:
| October 1st || delivery parts of Hunter (racks, APU and CPU nods, cooling, mgmt-systems, ...)
| October 1st || delivery parts of Hunter (racks, APU and CPU nods, cooling, mgmt-systems, ...)
|-
|-
| early November  || first appl tests by pilot users |-
| early November  || software installation and first application tests by pilot users  
|-
|-
| November 18th || delivery of lustre filesystems  
| November 18th || delivery of lustre filesystems  
Line 21: Line 21:
| Q4 / 2024 || Hawk will be reduced by another 8 racks (if projects are active on Hunter)
| Q4 / 2024 || Hawk will be reduced by another 8 racks (if projects are active on Hunter)
|-
|-
| January 31st || Acceptance Hunter and starting data migration onto new storage platform
| January 31st 2025 || Acceptance Hunter and starting data migration onto new storage platform
|-
|-
| end of April 2025 || Hawk final power down
| end of April 2025 || Hawk final power down

Latest revision as of 09:16, 31 October 2024

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

More information could be found [| hpc in transition hunter and herder will bring new opportunities new challenges] and [| exascale supercomputing is coming to stuttgart] fact-sheet can be found here.


time frame action
June 18th - 19th Hawk maintenance and preparation

of infrastructure (1st part). System will be reduced to 4096 compute nodes in total

October 1st delivery parts of Hunter (racks, APU and CPU nods, cooling, mgmt-systems, ...)
early November software installation and first application tests by pilot users
November 18th delivery of lustre filesystems
Q4 / 2024 Hawk will be reduced by another 8 racks (if projects are active on Hunter)
January 31st 2025 Acceptance Hunter and starting data migration onto new storage platform
end of April 2025 Hawk final power down
installation phase finished


The following illustration shows the current planning of the Hunter installation. Please note that the schedule is subject to change.

Installation planning as of June 2024