Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
mNo edit summary
No edit summary
Line 8: Line 8:
| end of May 2019|| Installation of a small test system
| end of May 2019|| Installation of a small test system
|-
|-
| September 2nd ... 6th || Reduce Cray XC40 HazelHen to ~3800 Nodes and
| September 2nd ... 6th || maintenance and preparation
preparation of infrastructure for Hawk  (1st part)
of infrastructure (1st part).
|-
|-
| October 2019|| Installation of a few racks Hawk, storage, pre-post servers, ...
| November 25th ... 28th || Reduce Cray XC40 HazelHen to ~3800 Nodes and
preparation of infrastructure for Hawk  (2nd part)
|-
| January 2020 || Installation of 8 racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users
integration, testing, setup for users
|-
|-
| November 2019 || Test Phase for pilot users  ~ 4 weeks
| January (~3rd week) || Test Phase for pilot users  ~ 3 weeks
|-
| February 11 2020 || Final shutdown and decommission of Hazel Hen
and preparation of infrastructure for the complete installation of Hawk
|-
|-
| December 2019 || Decommission of Hazel Hen and preparation of infrastructure for the
| until Februar 18th  || complete Hawk hardware installation
complete installation of Hawk
|-
|-
| later || complete Hawk hardware installation, testing, and integrate into
| until March 1st || testing, and integrate aadditional racks into
first phase
first phase
|-  
|-  
| more later || Acceptance and production
| more later || Acceptance and production
|}
|}

Revision as of 16:32, 4 July 2019

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 25th ... 28th Reduce Cray XC40 HazelHen to ~3800 Nodes and

preparation of infrastructure for Hawk (2nd part)

January 2020 Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

January (~3rd week) Test Phase for pilot users ~ 3 weeks
February 11 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk

until Februar 18th complete Hawk hardware installation
until March 1st testing, and integrate aadditional racks into

first phase

more later Acceptance and production