Hawk installation schedule: Difference between revisions
From HLRS Platforms
Jump to navigationJump to search
mNo edit summary |
No edit summary |
||
Line 8: | Line 8: | ||
| end of May 2019|| Installation of a small test system | | end of May 2019|| Installation of a small test system | ||
|- | |- | ||
| September 2nd ... 6th || | | September 2nd ... 6th || maintenance and preparation | ||
of infrastructure (1st part). | |||
|- | |- | ||
| | | November 25th ... 28th || Reduce Cray XC40 HazelHen to ~3800 Nodes and | ||
preparation of infrastructure for Hawk (2nd part) | |||
|- | |||
| January 2020 || Installation of 8 racks Hawk, storage, pre-post servers, ... | |||
integration, testing, setup for users | integration, testing, setup for users | ||
|- | |- | ||
| | | January (~3rd week) || Test Phase for pilot users ~ 3 weeks | ||
|- | |||
| February 11 2020 || Final shutdown and decommission of Hazel Hen | |||
and preparation of infrastructure for the complete installation of Hawk | |||
|- | |- | ||
| | | until Februar 18th || complete Hawk hardware installation | ||
complete installation | |||
|- | |- | ||
| | | until March 1st || testing, and integrate aadditional racks into | ||
first phase | first phase | ||
|- | |- | ||
| more later || Acceptance and production | | more later || Acceptance and production | ||
|} | |} |
Revision as of 16:32, 4 July 2019
This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
time frame | action |
---|---|
end of May 2019 | Installation of a small test system |
September 2nd ... 6th | maintenance and preparation
of infrastructure (1st part). |
November 25th ... 28th | Reduce Cray XC40 HazelHen to ~3800 Nodes and
preparation of infrastructure for Hawk (2nd part) |
January 2020 | Installation of 8 racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users |
January (~3rd week) | Test Phase for pilot users ~ 3 weeks |
February 11 2020 | Final shutdown and decommission of Hazel Hen
and preparation of infrastructure for the complete installation of Hawk |
until Februar 18th | complete Hawk hardware installation |
until March 1st | testing, and integrate aadditional racks into
first phase |
more later | Acceptance and production |