Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
Line 24: Line 24:
| until Februar 18th  || complete Hawk hardware installation
| until Februar 18th  || complete Hawk hardware installation
|-
|-
| until March 1st ||  testing, and integrate aadditional racks into
| until March 1st ||  testing, and integrate additional racks into
first phase
first phase
|-  
|-  
| more later || Acceptance and production
| more later || Acceptance and production
|}
|}

Revision as of 14:59, 5 November 2019

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 19th Reduce Cray XC40 HazelHen to ~3800 Nodes and

preparation of infrastructure for Hawk

January 2nd 2020 Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

January (~3rd week) Test Phase for pilot users ~ 3 weeks
February 11 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk

until Februar 18th complete Hawk hardware installation
until March 1st testing, and integrate additional racks into

first phase

more later Acceptance and production