Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
Line 16: Line 16:
| January 17th 2020 || Installation of 8 racks Hawk, storage, pre-post servers, ...
| January 17th 2020 || Installation of 8 racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users
integration, testing, setup for users
|-
| until Februar 18th  || complete Hawk hardware installation
|-
|-
| mid-February  || Test Phase for pilot users  ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
| mid-February  || Test Phase for pilot users  ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
|-
|-
| February 24 2020 || Final shutdown and decommission of Hazel Hen  
| February 24 2020 || Final shutdown and decommission of Hazel Hen  
and preparation of infrastructure for the complete installation of Hawk
and preparation of infrastructure for the complete installation of Hawk.
|-
|-
| until Februar 18th  || complete Hawk hardware installation
| February 25 2020 || hazelhen workspace filesystem (ws9) has been fully integrated with all workspaces into the hawk system.
|-
|-
| until March 1st ||  testing, and integrate additional racks into
| until March 1st ||  testing, and integrate additional racks into
first phase
first phase
|-
| until March 15 || prepare power and cooling facility for second phase hawk
|-
| even later || test and integrate all remaining cabinets into the hawk system
|-  
|-  
| even later || Acceptance and production
| even later || Acceptance and production

Revision as of 19:44, 25 February 2020

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 19th Reduce Cray XC40 HazelHen to ~4488 Nodes and

preparation of infrastructure for Hawk

January 17th 2020 Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

until Februar 18th complete Hawk hardware installation
mid-February Test Phase for pilot users ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
February 24 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk.

February 25 2020 hazelhen workspace filesystem (ws9) has been fully integrated with all workspaces into the hawk system.
until March 1st testing, and integrate additional racks into

first phase

until March 15 prepare power and cooling facility for second phase hawk
even later test and integrate all remaining cabinets into the hawk system
even later Acceptance and production
April / May Data migration by users from ws9 (Hazel Hen) onto ws10 (Hawk) filesystem