- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -

Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
Line 14: Line 14:
preparation of infrastructure for Hawk   
preparation of infrastructure for Hawk   
|-
|-
| January 8th 2020 || Installation of 8 racks Hawk, storage, pre-post servers, ...
| (January 8th) 2020 '''delay, please stay tuned''' || Installation of 8 racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users
integration, testing, setup for users
|-
|-
| January (~3rd week) || Test Phase for pilot users  ~ 3 weeks
| January (~3rd week), '''will be later...'''  || Test Phase for pilot users  ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed.
|-
|-
| February 11 2020 || Final shutdown and decommission of Hazel Hen  
| February 11 2020 || Final shutdown and decommission of Hazel Hen  

Revision as of 11:02, 27 December 2019

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 19th Reduce Cray XC40 HazelHen to ~4488 Nodes and

preparation of infrastructure for Hawk

(January 8th) 2020 delay, please stay tuned Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

January (~3rd week), will be later... Test Phase for pilot users ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed.
February 11 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk

until Februar 18th complete Hawk hardware installation
until March 1st testing, and integrate additional racks into

first phase

more later Acceptance and production