Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
Line 17: Line 17:
integration, testing, setup for users
integration, testing, setup for users
|-
|-
| mid-February  || Test Phase for pilot users  ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed.
| mid-February  || Test Phase for pilot users  ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
|-
|-
| February 24 2020 || Final shutdown and decommission of Hazel Hen  
| February 24 2020 || Final shutdown and decommission of Hazel Hen  
Line 28: Line 28:
|-  
|-  
| even later || Acceptance and production
| even later || Acceptance and production
|-  April / May || Data migration by users from ws9 (Hazel Hen) onto ws10 (Hawk) filesystem
|}
|}

Revision as of 17:47, 5 February 2020

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 19th Reduce Cray XC40 HazelHen to ~4488 Nodes and

preparation of infrastructure for Hawk

January 17th 2020 Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

mid-February Test Phase for pilot users ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
February 24 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk

until Februar 18th complete Hawk hardware installation
until March 1st testing, and integrate additional racks into

first phase

even later Acceptance and production