CRAY XE6 status
From HLRS Platforms
Jump to navigationJump to search
- 29.11.2010: Hardware of phase1 step 0 (installation step 0) was delivered
- 30.11.2010: Power on for step 0
- 02.12.2010: internal users and HWW environment for testing installed
- 10.12.2010: online documentation available
- 17.12.2010: internal training
- 21.12.2010: Final User Management configuration
- 27.12.2010: December Programming Environment Release installed
- 07.01.2011: Security Patches FN #5740 and FN#5752 installed
- 24.02.2011: Security Patches FN #5760
- 24.02.2011: February Programming Environment Release installed
- 23.03.2011: March Programming Environment Release installed
- 07.04.2011: Update to CLE 3.1.UP03
- 25.07.2011: Update to CLE 4.0 UP00 and SMW Upgrade
- 27.09.2011: Hardware delivery of installation step 1
- 28.09.2011: Final shutdown of step 0 for integration into step 1
- 04.10.2011: Power on for step 1
- 31.10.2011: Ready for use of step 1
- 29.11.2011: Stability test of step 1 starts; accessible for users
- 29.12.2011: System accepted and now in production