- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -
Hawk installation schedule
From HLRS Platforms
Jump to navigationJump to search
This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
time frame | action |
---|---|
end of May 2019 | Installation of a small test system |
September 2nd ... 6th | maintenance and preparation
of infrastructure (1st part). |
November 25th ... 28th | Reduce Cray XC40 HazelHen to ~3800 Nodes and
preparation of infrastructure for Hawk |
January 2020 | Installation of 8 racks Hawk, storage, pre-post servers, ...
integration, testing, setup for users |
January (~3rd week) | Test Phase for pilot users ~ 3 weeks |
February 11 2020 | Final shutdown and decommission of Hazel Hen
and preparation of infrastructure for the complete installation of Hawk |
until Februar 18th | complete Hawk hardware installation |
until March 1st | testing, and integrate aadditional racks into
first phase |
more later | Acceptance and production |