Hawk installation schedule
From HLRS Platforms
Jump to navigationJump to search
This page will be updated as new information becomes available
time frame | action |
---|---|
end of May 2019 | Installation of a small test system |
September 2nd ... 6th | Reduce Cray XC40 Hazel Hen to ~3800 Nodes and
preparation infrastructure for Hawk (1st part) |
October 2019 | Installation of 16 racks Hawk, storage, pre-post servers, …
integration, testing, setup for users |
November 2019 | Test Phase for pilot users ~ 4 weeks |
December 2019 | Decomission Hazel Hen and prepare infrastructure to
complete installation Hawk |
later | complete Hawk hardware installation, testing, and integrate into
fisrt phase |
more later | Acceptance and production |