- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -

Hunter installation schedule

From HLRS Platforms
Revision as of 12:15, 29 May 2024 by Hpctobei (talk | contribs)
Jump to navigationJump to search

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

More information could be found [hpc in transition hunter and herder will bring new opportunities new challenges] and [supercomputing kommt nach stuttgart] fact-sheet can be found here.


time frame action
June 18th - 20 Hawk maintenance and preparation

of infrastructure (1st part). System will be reduced to 4096 compute nodes in total

mid of August delivery parts of Hunter
January 31st Acceptance Hunter and starting data migration onto new storage platform
end of April Hawk final power down
installation phase finished