Difference between revisions of "Hawk installation schedule"

From HLRS Platforms
Jump to navigationJump to search
(Created page with "This page will be updated as new information becomes available")
 
Line 1: Line 1:
 
This page will be updated as new information becomes available
 
This page will be updated as new information becomes available
 +
 +
{| class="wikitable"
 +
|-
 +
! time frame !! action
 +
|-
 +
| end of May 2019|| Installation of a small test system
 +
|-
 +
| September 2nd ... 6th || Reduce Cray XC40 Hazel Hen to ~3800 Nodes and
 +
preparation infrastructure for Hawk  (1st part)
 +
|-
 +
| October 2019|| Installation of 16 racks Hawk, storage, pre-post servers, …
 +
integration, testing, setup for users
 +
|-
 +
| November 2019 || Test Phase for pilot users  ~ 4 weeks
 +
|-
 +
| December 2019 || Decomission Hazel Hen and prepare infrastructure to
 +
complete installation Hawk
 +
|-
 +
| later || complete Hawk hardware installation, testing, and integrate into
 +
fisrt phase
 +
|-
 +
| more later || Acceptance and production
 +
|}

Revision as of 14:48, 9 May 2019

This page will be updated as new information becomes available

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th Reduce Cray XC40 Hazel Hen to ~3800 Nodes and

preparation infrastructure for Hawk (1st part)

October 2019 Installation of 16 racks Hawk, storage, pre-post servers, …

integration, testing, setup for users

November 2019 Test Phase for pilot users ~ 4 weeks
December 2019 Decomission Hazel Hen and prepare infrastructure to

complete installation Hawk

later complete Hawk hardware installation, testing, and integrate into

fisrt phase

more later Acceptance and production