This page will be updated as new information becomes available
+
This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge
 +
components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...
  
 
{| class="wikitable"
 
{| class="wikitable"

Revision as of 14:54, 9 May 2019

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th Reduce Cray XC40 Hazel Hen to ~3800 Nodes and

preparation infrastructure for Hawk (1st part)

October 2019 Installation of 16 racks Hawk, storage, pre-post servers, …

integration, testing, setup for users

November 2019 Test Phase for pilot users ~ 4 weeks
December 2019 Decomission Hazel Hen and prepare infrastructure to

complete installation Hawk

later complete Hawk hardware installation, testing, and integrate into

fisrt phase

more later Acceptance and production