- Infos im HLRS Wiki sind nicht rechtsverbindlich und ohne Gewähr -
- Information contained in the HLRS Wiki is not legally binding and HLRS is not responsible for any damages that might result from its use -

Hawk installation schedule: Difference between revisions

From HLRS Platforms
Jump to navigationJump to search
No edit summary
No edit summary
Line 28: Line 28:
| until March 1st ||  testing, and integrate additional racks into
| until March 1st ||  testing, and integrate additional racks into
first phase (2048 nodes)
first phase (2048 nodes)
|-
| early March || general availability for all users
|-
|-
| until March 15 || prepare power and cooling facility for second phase hawk
| until March 15 || prepare power and cooling facility for second phase hawk

Revision as of 19:50, 25 February 2020

This page will be updated as new information becomes available. Please be aware, HPC systems are made out of leading edge components. If one of this components is delayed, the complete schedule will change. Do not take this schedule too serious...

time frame action
end of May 2019 Installation of a small test system
September 2nd ... 6th maintenance and preparation

of infrastructure (1st part).

November 19th Reduce Cray XC40 HazelHen to ~4488 Nodes and

preparation of infrastructure for Hawk

January 17th 2020 Installation of 8 racks Hawk, storage, pre-post servers, ...

integration, testing, setup for users

until Februar 18th complete Hawk hardware installation
mid-February Test Phase for pilot users ~ 3 weeks. Due to the delayed delivery, the test phase will also be postponed. The filesystem will be ws9 (Hazel Hen)
February 24 2020 Final shutdown and decommission of Hazel Hen

and preparation of infrastructure for the complete installation of Hawk.

February 25 2020 hazelhen workspace filesystem (ws9) has been fully integrated with all workspaces into the hawk system.
until March 1st testing, and integrate additional racks into

first phase (2048 nodes)

early March general availability for all users
until March 15 prepare power and cooling facility for second phase hawk
later test and integrate all remaining cabinets into the hawk system (5632 nodes total)
even later Acceptance and production
April / May Data migration by users from ws9 (Hazel Hen) onto ws10 (Hawk) filesystem